Time Remaining Question 69 01:03:09 What is the MINIMUM length of time it will

Question: Time Remaining Question 69 01:03:09 What is the MINIMUM length of time it will take to complete the project through Task “H”? 1. 7 days 2. 8 days 9 days 10 days 3. 4. A Critical Path Chart B C E F D G Task Days A B DUDEG 44252LL G 2 H 1 I 1 enlarge image Question Answered 56 0-0See the answerSee the answerSee the answer done loading
Show transcribed image textAnswer: Correct Option i…View the full answerTranscribed image text: Time Remaining Question 69 01:03:09 What is the MINIMUM length of time it will take to complete the project through Task “H”? 1. 7 days 2. 8 days 9 days 10 days 3. 4. A Critical Path Chart B C E F D G Task Days A B DUDEG 44252LL G 2 H 1 I 1 enlarge image Question Answered 56 0-0