SECTION B [20 marks] The network for a small project is shown in Figure

Question: SECTION B [20 marks] The network for a small project is shown in Figure B along with the resources associated with each activity. The durations are in days. Copy the network onto the Sheet ‘Template for Section B’ and use it to answer questions B1 to B3 Activity Resources FIGURE B A Project Manager, Marketer 0 3 3 B Project Manager, Accountant A C Marketer 9help with b2 pls

Show transcribed image textTranscribed image text: SECTION B [20 marks] The network for a small project is shown in Figure B along with the resources associated with each activity. The durations are in days. Copy the network onto the Sheet ‘Template for Section B’ and use it to answer questions B1 to B3 Activity Resources FIGURE B A Project Manager, Marketer 0 3 3 B Project Manager, Accountant A C Marketer 9 12 D Administrator Start E Marketer, IT 0 1 1 F B Project Manager Accountant, IT G 0 1 1 B1) Use the template on the sheet ‘Template for Section B’ to produce an Activity Gantt Chart for the project. B2) Use the template on the sheet ‘Template for Section B’ to produce a Resource Gantt Chart for the project. B3) Now use the Resource Gantt chart from question B2 to manage the resources. Note that all resources must retain their allotted tasks. Produce a second resource Gantt chart on the sheet ‘Template for Section B’ to show any changes you have made ✓ A 3 12 1 4 C 9 G 7 16 10 10 7 16 10 17 10 10 3 D 2 E 9 F 10 19 12 19 19 19 Finish