Question: Question Time Remaining Question Answered 74 00:58:27 56 If Task “F” takes three days longer to complete than planned, how many days will be added to the estimated completion time of project? 1. 3 ABC Construction CPM Chart 201 2. 2 3. 1 4. 0 TDOS THE B Takc TaskD SARD 9 4 Days E) Task E Tak F Task H FORM Days 4086 3066 4 Days SDS 4 Day Task Task J Tack K
Show transcribed image textPaths: ABCEFGK =7 5 2 3 8 4 =29 days ABCEFHK =7 5 2 3 4 5 =26 days…View the full answerTranscribed image text: Question Time Remaining Question Answered 74 00:58:27 56 If Task “F” takes three days longer to complete than planned, how many days will be added to the estimated completion time of project? 1. 3 ABC Construction CPM Chart 201 2. 2 3. 1 4. 0 TDOS THE B Takc TaskD SARD 9 4 Days E) Task E Tak F Task H FORM Days 4086 3066 4 Days SDS 4 Day Task Task J Tack K