Question Time Remaining Question Answered 74 00:16:59 69 If Task “F” takes three days

Question: Question Time Remaining Question Answered 74 00:16:59 69 If Task “F” takes three days longer to complete than planned, how many days will be added to the estimated completion time of the project? 1. 3 ABC Construction CPM Chart 201 2. 2 3. 1 4. 0 A B C D THAB TaskC TaskD 3 Days 4 Days E F Days Task E Tak F Tak G H Task H onlarge image PDRYS 4086 3066 I 2 KSee the answerSee the answerSee the answer done loading

Show transcribed image textAnswer: 74. Op…View the full answerTranscribed image text: Question Time Remaining Question Answered 74 00:16:59 69 If Task “F” takes three days longer to complete than planned, how many days will be added to the estimated completion time of the project? 1. 3 ABC Construction CPM Chart 201 2. 2 3. 1 4. 0 A B C D THAB TaskC TaskD 3 Days 4 Days E F Days Task E Tak F Tak G H Task H onlarge image PDRYS 4086 3066 I 2 K 5DRS Task Dave Prov Business Procedures 821118068 43Li 75 How many work days will pass before Task “G” commences? 1. 22 2. 27 3. 33 4. 40 A 00:16:22 TDBS HEGO C Task A TackB Task C TaskD ABC Construction CPM Chart 2045 6 D 4086 $2 4 DES Days E Task E F Task F G Tak G H Task H onlarge image SUBS I questions offered 69 4 Days SUBE Task J Task K