Question Time Remaining Question Answered 73 00:31:16 67 If Task “I” takes two days

Question: Question Time Remaining Question Answered 73 00:31:16 67 If Task “I” takes two days longer to complete than planned, how many days will be added to the estimated completion time of the project? 1. 3 ABC Construction CPM Chart 2. 2 3. 1 4. 0 7001 201 B 6035 40as Tack A TaskD 8 Days F TakE Task H @DH 40as SUAS stan SUBS I DAVE Task Task J Tack K
Show transcribed image textANSWER 73 Option 4 – 0 . Explanation The Critical path of the project i…View the full answerTranscribed image text: Question Time Remaining Question Answered 73 00:31:16 67 If Task “I” takes two days longer to complete than planned, how many days will be added to the estimated completion time of the project? 1. 3 ABC Construction CPM Chart 2. 2 3. 1 4. 0 7001 201 B 6035 40as Tack A TaskD 8 Days F TakE Task H @DH 40as SUAS stan SUBS I DAVE Task Task J Tack K