Question Time Remaining 01:01:43 Question Answered 56 71 By the end of what day

Question: Question Time Remaining 01:01:43 Question Answered 56 71 By the end of what day will the project be complete if Task 3 is delayed from starting by 2 extra days? Assume that only Task 5 is dependent on the completion of Task 3. 22 23 24 25 26 27 28 29 30 31 1. 28 Task/Day Task 1 Task 2 2. 29 Task 3 Task 4 3. 30 Task 5 4. 31 enlarge imageSee the answerSee the answerSee the answer done loading
Show transcribed image textAnswer: Option 3. Day 30 Explanation: Current start date of task 3 = Day 25 Duration of task…View the full answerTranscribed image text: Question Time Remaining 01:01:43 Question Answered 56 71 By the end of what day will the project be complete if Task 3 is delayed from starting by 2 extra days? Assume that only Task 5 is dependent on the completion of Task 3. 22 23 24 25 26 27 28 29 30 31 1. 28 Task/Day Task 1 Task 2 2. 29 Task 3 Task 4 3. 30 Task 5 4. 31 enlarge image