Question 2 (6 marks) The Gantt Chart of a project is as following: 19

Question: Question 2 (6 marks) The Gantt Chart of a project is as following: 19 Jul 21 Resource Mode Task Name – Duration – Start Finish Names ✓ Add New Column M 1 Task A 1 day Wed 14 Wed 14 ✰ Task B 2 days Fri 16/0 Mon 19 ✰ Task C 2 days Tue 20/ Wed 21 ✰ Task D 1 day Tue 20/Tue 20/ * Task E 1 day Thu 22/ Thu 22/ 6 Task F 0.5 day: Thu 22/ Thu 22/ 7 ✰ Task G 1 daysubject: PROJECT MANAGEMENT RISK AND RELIABILITY

Show transcribed image textTranscribed image text: Question 2 (6 marks) The Gantt Chart of a project is as following: 19 Jul 21 Resource Mode Task Name – Duration – Start Finish Names ✓ Add New Column M 1 Task A 1 day Wed 14 Wed 14 ✰ Task B 2 days Fri 16/0 Mon 19 ✰ Task C 2 days Tue 20/ Wed 21 ✰ Task D 1 day Tue 20/Tue 20/ * Task E 1 day Thu 22/ Thu 22/ 6 Task F 0.5 day: Thu 22/ Thu 22/ 7 ✰ Task G 1 day Mon 19 Mon 19 B Task H 1 day Fri 16/0 Mon 19 Using the above Gantt Chart, answer the following questions: a) Which activities have slack? Briefly explain why? b) Which activity (activities) has (have) start-to-finish dependency? Briefly explain why? c) Which activity (activities) has (have) start-to-start dependency? Briefly explain why? d) Which activity (activities) has (have) finish-to-finish dependency? Briefly explain why? e) Which activity (activities) has (have) finish-to-start dependency? Briefly explain why? 2 3 4 5 5