In the following table the activities with their precedence sequence and expected time​ (days) are

Question: In the following table the activities with their precedence sequence and expected time​ (days) are listed for a project on which Carl​ Betterton’s construction company is​ working: Activity Immediate​ Predecessor(s) Time​See the answerSee the answerSee the answer done loadingIn the following table the activities with their precedence sequence and expected time​ (days) are listed for a project on which Carl​ Betterton’s construction company is​ working:

Activity
Immediate​ Predecessor(s)
Time​ (days)
A

7
B
A
4
C
A
6
D
B
6
E
B
4
F
C
4
G
D
6
H
​E, F
9
1. ​Carl’s team should be able to complete the project in ___________ days.
2.
What is the critical path for​ Carl’s project?
Group of answer choices
What is the critical path for​ Carl’s project?
A-C-F-H
A-B-E-H
A-B-D-G
A-C-E-G
100% (1 rating)ES, EF through forward pass: ES of A (no predecessor) =0 EF of all activities =ES time ES of B, C =EF of predecessor A ES of D, E =EF of B ES of F =EF of C ES of G =EF of D ES o…View the full answer