Heather​ Adams, production manager for a Colorado exercise equipment​ manufacturer, needs to schedule an order

Question: Heather​ Adams, production manager for a Colorado exercise equipment​ manufacturer, needs to schedule an order for 50​ UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume​ lot-for-lot ordering.Heather​ Adams, production manager for a Colorado exercise equipment​ manufacturer, needs to schedule an order for 50​ UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume​ lot-for-lot ordering.

Show transcribed image textAnswer: Part (a): The CORRECt OPTION = Option C Reason: The lead time given in options B and D is shown as wro…View the full answerTranscribed image text: The product structure is as follows: b) Choose the correct time-phased structure. O A. Ⓡ A stepper B D OB. F E F D Time in weeks c) Develop a net material requirements plan for F (enter your responses as whole numbers). 1: More Info A B C Time in weeks Item F stepper Q Q Gross req On hand Net req Order receipt Order release 1 D(1) A(2) 2 Item Stepper A B C D E F F(3) Lead Time 2 1 2 3 2 2 2 Stepper B(3) E(2) F(2) D E Week 3 On-Hand Inventory 10 20 20 10 15 5 20 E 4 C(2) D(2) E(1) stepper Time in weeks Components A(2), B(3), C(2) D(1) F(3) E(2), F(2) D(2): E(1) 5 O 6 7 8 Lead Time (weeks) OD. F DH EH R Time in weeks Q G stepper