Given the following information on four jobs currently in queue at Work Center 301: Job Job time(days) Due date(days from now) Remaining Time(days) Remaining number of

Question: Given the following information on four jobs currently in queue at Work Center 301: Job Job time(days) Due date(days from now) Remaining Time(days) Remaining number ofSee the answerSee the answerSee the answer done loadingGiven the following information on four jobs currently in queue at Work Center 301:
Job Job time(days) Due date(days from now) Remaining Time(days) Remaining number of operations A 3 15 6 2 B 7 20 8 4 C 6 25 5 2 D 4 10 3 3
Which Job should be processeded first based on Slack per Remaining Operation?
a.Job A
b. Job C
c. Job D
d. Job B
Answer: C. Job D Explanation: Based on the amount of slack available for each remaining operation, Job D needs to be completed first. A job’s slack per remaining operation can be thought of as a measurement of the amount of time that is available to…View the full answer