Given the following information on four jobs currently in queue at Work Center 301: Job Job time(days) Due date(days from now) Remaining Time(days) Remaining number of operations

Question: Given the following information on four jobs currently in queue at Work Center 301: Job Job time(days) Due date(days from now) Remaining Time(days) Remaining number of operationsGiven the following information on four jobs currently in queue at Work Center 301:
Job Job time(days) Due date(days from now) Remaining Time(days) Remaining number of operations A 3 15 6 2 B 7 20 8 4 C 6 30 5 3 D 4 20 3 2 Which Job should be processeded first based on the Critical Ratio priority rule?
a. Job B
b. Job C
c. Job D
d. Job A