Burns Boats wants to assemble 30 boats per 6​-hour ​day, using a production line. Total

Question: Burns Boats wants to assemble 30 boats per 6​-hour ​day, using a production line. Total task time for each boat is 50 minutes. a. The takt time is (enter your response here) minutes per boat. ​(Enter your response rounded to one decimal​ place.) The theoretical minimum number of workstations is (enter your response here). ​(Enter your response rounded up toBurns Boats wants to assemble 30 boats per 6​-hour ​day, using a production line. Total task time for each boat is 50 minutes.
a. The takt time is (enter your response here) minutes per boat. ​(Enter your response rounded to one decimal​ place.)
The theoretical minimum number of workstations is (enter your response here).
​(Enter your response rounded up to the next whole​ number.)
b. Suppose the longest individual task takes 16 minutes. Will Burns be able to accomplish its​ goal?
Solution: Given data, Time available = 6 hours ~ 360 minutes Desired output = 30 boats Total task…View the full answer