Bill of Material for Office Table Table Final Assembly Top Assembly Support Assembly (1

Question: Bill of Material for Office Table Table Final Assembly Top Assembly Support Assembly (1 required) (1 required) Bracket (6 required) Wood Screw (48 required) Center Support (1 required) Side Support (2 required) MS.53 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graphic above shows the bill
Show transcribed image text 100% (1 rating)Here, as per the available data, we can have the MRP plan for Office Table Final Assembly and Table-Top Assembly as follows: Formulas used: Gross requirements of period (G)= number of units of item used in parent unit*Planned order release of parent…View the full answerTranscribed image text: Bill of Material for Office Table Table Final Assembly Top Assembly Support Assembly (1 required) (1 required) Bracket (6 required) Wood Screw (48 required) Center Support (1 required) Side Support (2 required) MS.53 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graphic above shows the bill of material for this item. Below are the MRP tables for the top-level assembly (the Office Table Final Assembly) and one of its sub-assemblies (the Table-Top Assembly): Office Table Final Assembly Gross Requirements 8/1 8/8 8/15 8/22 8/29 9/5 200 400 600 9/12 9/19 9/26 500 500 200 Scheduled Receipts Projected On-Hand Inv. Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) Lot Size Table-Top Assembly 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 Gross Requirements Scheduled Receipts 190 Projected On-Hand Inv. Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) 2 10 Lot Size For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19? Number For the Office Table above, what are the Planned Order Receipts in the week of 8/8? Number For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19? Number For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5? Number 360 1 75 8/1 120