AON analysis problems Activity Preceding Time A 8 B 3 C A 7 D

Question: AON analysis problems Activity Preceding Time A 8 B 3 C A 7 D A,B 3 E C 4 F D 9 What is project completion time? What is the slack of activity B? What is the slack of activity C? What is the ES of activity D? What is the LF of activity D?Activity Preceding Time

Show transcribed image textTranscribed image text: AON analysis problems Activity Preceding Time A 8 B 3 C A 7 D A,B 3 E C 4 F D 9 What is project completion time? What is the slack of activity B? What is the slack of activity C? What is the ES of activity D? What is the LF of activity D?