A company is designing a product layout for a new product. It plans to

Question: A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Time Task Predecessor (seconds) A 50 B A 36 C 26 D 22 E B, D 70 F C, E 30 What is the total time for all theShow transcribed image textAnswer The total time is 234.00 seconds Activity Pre…View the full answerTranscribed image text: A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Time Task Predecessor (seconds) A 50 B A 36 C 26 D 22 E B, D 70 F C, E 30 What is the total time for all the tasks (in seconds)? (Answer: a number with two decimal places i.e. 22.00, 48.60) Answer: