2) The promoter of a rock concert must perform the following activities in order

Question: 2) The promoter of a rock concert must perform the following activities in order to concert can be held. Durations are in weeks. a) Draw Gant chart and CPM diagrams? (30p) b) Specify the critical path and duration to complete the project? (20p) Table 1: Concert Project Activity Predecessor(s) Durations A: Find site 3 B. Find Engineers A 2 C: Hire opening act

Show transcribed image textTranscribed image text: 2) The promoter of a rock concert must perform the following activities in order to concert can be held. Durations are in weeks. a) Draw Gant chart and CPM diagrams? (30p) b) Specify the critical path and duration to complete the project? (20p) Table 1: Concert Project Activity Predecessor(s) Durations A: Find site 3 B. Find Engineers A 2 C: Hire opening act A 6 D: Set radio and TV ads C E: Set up ticket agents A F: Prepare electronics B G: Print advertising C H: Setup transportation C 1: Rehearsals F,H J: Last minute details I 3 3 3 5 1 2 2