2. The following questions refer to the table data for jobs awaiting processing at

Question: 2. The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival): Processing Time Due Date Job (days) (days) 2 2 5 6 7 8 3 8 What is the average flow time for the minimum slack time (MST) priority rule schedule (using the CR rule to break ties)? Average job lateness? Average WIP atSee the answerSee the answerSee the answer done loading
Show transcribed image text 100% (1 rating)BUT THE SLACK TIME FOR JIBS B AND C ARE THE SAME. SO FOR SEQUENCING PURPOSES, THE CRITICAL RATIO (CR ) WILL BE CALCULATED WHICH IS A RATIO OF TIME REMAINING AND THE PROCES…View the full answerTranscribed image text: 2. The following questions refer to the table data for jobs awaiting processing at a single work station (jobs are shown in order of arrival): Processing Time Due Date Job (days) (days) 2 2 5 6 7 8 3 8 What is the average flow time for the minimum slack time (MST) priority rule schedule (using the CR rule to break ties)? Average job lateness? Average WIP at the centre? ABCO A C D